← Dashboard
Old House · Pro Hire · Exterior
Exterior Paint — Side & Patio Wall
STATUS Quote received · Expired · Renewal needed
QUOTE DATE Mar 26, 2025
EST # EST-000102
CONTRACTOR Pro Quality Painting & Home Repair LLC
⚠ Quote Expired — Renewal Required
Original quote expired Apr 2, 2025. Quote does not include siding replacement, which photo assessment suggests will be required on at least a portion of the wall. Request a revised quote that includes a siding replacement line item with per-board or per-linear-foot pricing before signing.
Quote Summary
Base Quote
$6,900
Paint only · No siding replacement
Estimated Final Range
$6,700–$8,500
Known repairs already included · adder only if additional damage found
Lead Status
Lead Free
Standard practices · no encapsulation required · lighter abatement
Scope of Work (Per Quote)
Siding Replacement Cost Estimator
Assumptions
This wall is lead free — no encapsulation cost on siding work. Dennis has already identified and priced a few short clapboard lengths and one window sill/casing on the back side. This table shows the adder cost only for any additional boards discovered beyond what's already in the quote.
Reference unit: one standard clapboard board = approx. 16 ft long × 4" face exposure.
Boards to Replace Approx. Linear Ft Material Est. Labor Est. Siding Adder Total w/ $6,700 Base
5 boards 80 lf $120–$180 $400–$600 $520–$780 $7,220–$7,480 Minor
10 boards 160 lf $240–$360 $800–$1,200 $1,040–$1,560 $7,740–$8,260 Moderate
20 boards 320 lf $480–$720 $1,600–$2,400 $2,080–$3,120 $8,780–$9,820 Likely
30 boards 480 lf $720–$1,080 $2,400–$3,600 $3,120–$4,680 $9,820–$11,380 Worst Case
Most likely range — known repairs included, minimal additional expected $500–$1,500 $7,500–$9,000
* Estimates based on regional CT contractor rates. Actual adder depends on Dennis's per-board pricing — request this explicitly when renewing the quote.
Payment Schedule (Original Quote)
Security Deposit
Due at contract signing
$500
Down Payment
Due 1 week prior to start
$4,000
Balance Due
Due at completion
$2,400
Next Actions
01
Contact Dennis to renew the quote — original expired Apr 2, 2025. Request a revised version that adds a siding replacement line item with explicit per-board or per-linear-foot pricing so scope increases are priced transparently.
02
Walk the wall with Dennis before signing. Agree on a board count threshold — e.g. "up to 15 boards included at $X/board, anything over requires a change order." This caps surprise costs.
03
Confirm lead-safe disposal plan and CT RRP certification. Verify Dennis holds an active EPA RRP contractor certification — required for disturbance of this scale on a pre-1978 home.
04
Finalize color scheme before contract signing — the quote lists this as TBD. Color selection affects primer spec and may affect material cost.
05
Coordinate electrical panel access and cable routing on the right corner — masking alone may not be sufficient. Confirm Dennis's plan for working around the panel and conduit runs.
Questions to Ask Dennis — Pro Research Panel
Lead & Certification
Siding Replacement Scope & Pricing
Workmanship & Contract
Site Logistics
Cost Levers
Reduce Cost
  • Agree a board count cap with a change order threshold upfront — prevents open-ended siding scope creep.
  • Lock in color before he starts — color TBD can delay primer selection and add a mobilization cost.
  • Clear the work area yourself — move the propane tank, remove the iron furniture, clear foundation plantings. Less setup = less billed labor.
  • Bundle front or side wall into the same mobilization. Dennis will likely discount the per-wall rate if two or more walls are done together.
Watch These
  • Subsurface rot — lower course near grade is highest risk. Sheathing repair if found is not in any current estimate.
  • Reglazing scope — in the quote but labor-intensive on lead-positive wood. Ask how many windows are included.
  • Color selection — darker colors may require 3 coats on heavily repaired surfaces. Ask if color affects price.
  • Storm window swap — if you replace the storm before he paints, the reglazing line item changes. Confirm he'll adjust scope.
Storm Window Replacement — Sequencing Decision
✓ Replace Storm Window First — Before Dennis Starts
Install the new storm window before Dennis mobilizes. This is not a race — it's the correct order of operations.
Why Storm First
What to Tell Dennis
Storm Window Selection Notes — 1830 Historic Property